Bridge that Gap: Great Central Railway News

Discussion in 'Heritage Railways & Centres in the UK' started by Gav106, May 8, 2010.

  1. brmp201

    brmp201 Member

    Joined:
    May 18, 2010
    Messages:
    681
    Likes Received:
    1,090
    Gender:
    Male
    Occupation:
    IT Director
    Location:
    Surrey, UK
    Heritage Railway Volunteer:
    No I do not currently volunteer
    Now on the GCR website - Tender time for the Factory Flyover! - Great Central Railway
     
    Bluenosejohn, Johnme101 and jnc like this.
  2. Flying Phil

    Flying Phil Part of the furniture

    Joined:
    Dec 10, 2018
    Messages:
    3,197
    Likes Received:
    7,143
    Gender:
    Male
    Location:
    Leicestershire
    Heritage Railway Volunteer:
    Yes I am an active volunteer
    The "Urban Viaduct" I think is effectively going to be three parts. From the two track canal bridge, there will be approx 60m of embankment then a small single track bridge next to the Combined Sewer Outflow to allow maintenance vehicle access. Then it is the single track precast sections of the Urban Viaduct (About 250m), steadily rising to meet the Railway Terrace crossing bridge. This bridge is the highest point to allow for the large tip lorries to get to the recycling centre.
    There is also a small section of North embankment to be rebuilt, to join the MML bridge to the existing embankment and Chord line track.
    The existing Engine Shed will need to be relocated as the twin tracks to the Canal Bridge are on the original track formation - which is roads 1 and 2 in the shed. That is still three to five years away though.
     
  3. brmp201

    brmp201 Member

    Joined:
    May 18, 2010
    Messages:
    681
    Likes Received:
    1,090
    Gender:
    Male
    Occupation:
    IT Director
    Location:
    Surrey, UK
    Heritage Railway Volunteer:
    No I do not currently volunteer
  4. Flying Phil

    Flying Phil Part of the furniture

    Joined:
    Dec 10, 2018
    Messages:
    3,197
    Likes Received:
    7,143
    Gender:
    Male
    Location:
    Leicestershire
    Heritage Railway Volunteer:
    Yes I am an active volunteer
    That is a good video update and the projected build time is better than I thought it would be....complete by Christmas next year!
     
  5. jnc

    jnc Well-Known Member

    Joined:
    Apr 3, 2012
    Messages:
    1,820
    Likes Received:
    3,163
    Gender:
    Male
    Location:
    Western Atlantic
    Heritage Railway Volunteer:
    No I do not currently volunteer
    For those of us who refuse to watch videos: What is it that will be complete by Christmas next? Just the car park viaduct and the bridge over the road (which is what they are currently accumulating money for), or something else as well?

    Noel
     
  6. Mark Thompson

    Mark Thompson Well-Known Member

    Joined:
    Sep 10, 2017
    Messages:
    1,897
    Likes Received:
    4,652
    Gender:
    Male
    Location:
    E sussex
    Heritage Railway Volunteer:
    No I do not currently volunteer
    Yes. Exactly that. The most difficult bit in terms of logistics. The "Urban Viaduct", which has no direct third party involvement, would be a separate and final phase.
     
    jnc likes this.