    Is the Grosmont Co-op now the NYMR's official communications agency?

    Tom
     
    Sheff, Diamond Gaz, green five و 10 آخرون معجبون بهذا.
  2. 5944

    5944 Resident of Nat Pres

    إنضم إلينا في:
    ‏14 يناير 2006
    المشاركات:
    9,998
    عدد المعجبين:
    11,987
    الجنس:
    ذكر
    الوظيفة:
    Train Maintainer for GTR at Hornsey
    مكان الإقامة:
    Letchworth
    Heritage Railway Volunteer:
    No I do not currently volunteer
    It's certainly a lot easier getting information out of them!
     
    banburysaint, green five, Paul42 و 6 آخرون معجبون بهذا.
  3. Kirk Oswald

    Kirk Oswald New Member

    إنضم إلينا في:
    ‏1 إبريل 2024
    المشاركات:
    69
    عدد المعجبين:
    152
    مكان الإقامة:
    Kirkoswald
    Heritage Railway Volunteer:
    Yes I am an active volunteer
    I know the Grosmont Post Office team and they always try and "look after" the village in the nicest possible way. I also know from bitter experience that the NYMR Park Street Mafia deceive, distort and obfuscate at every opportunity.

    I wasn't at the meeting last night (had to be elsewhere) but know from first hand reports that it was the expected PR performance. Reassurances were offered and in theory work starts today on propping the structure, the railway having just about raised the £250,000 to pay for the first part of the project. Completion of repairs is said to be scheduled for Winter 2026/27 which is a sensible timeframe.

    However there is no assurance that an additional £500,000 or more can be raised to fund the actual work. Meanwhile the scaffolding will be a liability in terms of the rental being paid until the work has been done.
     
    banburysaint, green five, oldmrheath و 3 آخرون معجبون بهذا.
  4. 47406

    47406 Well-Known Member

    إنضم إلينا في:
    ‏24 اكتوبر 2006
    المشاركات:
    1,445
    عدد المعجبين:
    215
    الجنس:
    ذكر
    الوظيفة:
    Operations Manager
    مكان الإقامة:
    County Durham
    So now we are up to v2.6 of the timetable, so 9th edition.
     
  5. cksteam

    cksteam Member

    إنضم إلينا في:
    ‏25 أوت 2011
    المشاركات:
    313
    عدد المعجبين:
    403
    الجنس:
    ذكر
    الوظيفة:
    Planning
    مكان الإقامة:
    Halifax, West Yorkshire
    Heritage Railway Volunteer:
    No I do not currently volunteer
    Is it too late to get a sweepstake going to guess the final number?
     
    أعجب بهذه المشاركة 47406
  6. 5944

    5944 Resident of Nat Pres

    إنضم إلينا في:
    ‏14 يناير 2006
    المشاركات:
    9,998
    عدد المعجبين:
    11,987
    الجنس:
    ذكر
    الوظيفة:
    Train Maintainer for GTR at Hornsey
    مكان الإقامة:
    Letchworth
    Heritage Railway Volunteer:
    No I do not currently volunteer
    15th day of normal services and they're already on the ninth timetable?! :eek:
     
    أعجب بهذه المشاركة 47406
  7. jnc

    jnc Well-Known Member

    إنضم إلينا في:
    ‏3 إبريل 2012
    المشاركات:
    1,702
    عدد المعجبين:
    2,939
    الجنس:
    ذكر
    مكان الإقامة:
    Western Atlantic
    Heritage Railway Volunteer:
    No I do not currently volunteer
    Some element(s) of the bridge 42 repair (the initial report wasn't very detailed) - either the propping (if there is such - see below) or the repair itself.

    I say "propping (if there is such" because the 'Essential Maintenance Work' document says nothing about propping! It only talks about "temporary access scaffolding". It describes that thusly: "scaffold will comprise a series of beams spanning longitudinally across the bridge above parapet level. At each bearing point, the structure will be protected using foam and soft timber pattresses to prevent damage to the masonry. No drilling or fixings into the masonry arches will be required; the scaffold will be entirely free-standing. All scaffold loading will be carefully assessed to ensure compatibility with the bridge’s load-bearing capacity."

    I'm not quite sure what that last sentence means/implies, but the overall vibe I get from the entire quoted segment is that the scaffolding is just for worker access, and to hold up the newly-replaced brickwork (while the concrete cures); not as temporary means to support the bridge structure. In fact, the impression I get is that the scaffolding might be leaning on the bridge ("bearing point") - but at the same time it says "the scaffold will be entirely free-standing".

    I confess I don't fully understand the quoted description; if anyone can enlighten me I'd be grateful.

    PS: It's possible that the propping is not covered at all in the "Essential Maintenance Work" document (but it should be in the environment paperwork, since it'll have to be standing in the river). Since it's apparently about to start shortly, we shall soon see.

    Noel
     
    Last edited: ‏14 إبريل 2026
    أعجب بهذه المشاركة Sheff
  8. jnc

    jnc Well-Known Member

    إنضم إلينا في:
    ‏3 إبريل 2012
    المشاركات:
    1,702
    عدد المعجبين:
    2,939
    الجنس:
    ذكر
    مكان الإقامة:
    Western Atlantic
    Heritage Railway Volunteer:
    No I do not currently volunteer
    It's possible that the repair scaffolding (see above) is a separate thing from the 'propping' (about which I see nothing anywhere in the planning application, all of which I quickly just reviewed), and that the scaffolding will only be installed shortly before the main repair work starts. If so, that would cut down on the scaffolding rental costs.

    (If anyone could point me at any documentation on the 'propping' I would be grateful.)

    Noel
     
  9. Sulzerman

    Sulzerman Member

    إنضم إلينا في:
    ‏22 يناير 2025
    المشاركات:
    209
    عدد المعجبين:
    266
    الجنس:
    ذكر
    مكان الإقامة:
    Malton
    Heritage Railway Volunteer:
    No I do not currently volunteer
    Sheff و jnc معجبون بهذا.
  10. Steve

    Steve Nat Pres stalwart Friend

    إنضم إلينا في:
    ‏7 اكتوبر 2006
    المشاركات:
    13,438
    عدد المعجبين:
    13,739
    الوظيفة:
    Gentleman of leisure, nowadays
    مكان الإقامة:
    Near Leeds
    Heritage Railway Volunteer:
    Yes I am an active volunteer
    The propping and repairs are two separate things. The repairs require planning permission as it is a listed structure and will be invasive. The propping is not and is not referred to in the planning application. The scaffolding referred to in the planning is for access and is free standing in that it is not physically attached to the bridge. However, it will rest on the bridge, as I understand it.
     
    أعجب بهذه المشاركة jnc
  11. std tank

    std tank Part of the furniture

    إنضم إلينا في:
    ‏20 سبتمبر 2005
    المشاركات:
    4,008
    عدد المعجبين:
    1,141
    الجنس:
    ذكر
    الوظيفة:
    Retired
    مكان الإقامة:
    Liverpool
    Heritage Railway Volunteer:
    Yes I am an active volunteer
    Surely, the scaffolding will be required, from the riverbed upwards, to enable the propping to be built.
     
  12. Andy Williams

    Andy Williams Well-Known Member

    إنضم إلينا في:
    ‏23 إبريل 2010
    المشاركات:
    1,112
    عدد المعجبين:
    1,124
    الوظيفة:
    Design Engineer
    مكان الإقامة:
    Shropshire
    Heritage Railway Volunteer:
    Yes I am an active volunteer
    I believe that the components used to form the propping are on hire from a supplier, and will need to remain in place until early 2027.

    If the crane is due to arrive on Monday 20th April, that constitutes a slippage of two weeks on the original four week programme. The proposed re-opening date of 2nd May may now be in doubt.
     
    Last edited: ‏14 إبريل 2026
    jnc, 35B و 47406 معجبون بهذا.
  13. jnc

    jnc Well-Known Member

    إنضم إلينا في:
    ‏3 إبريل 2012
    المشاركات:
    1,702
    عدد المعجبين:
    2,939
    الجنس:
    ذكر
    مكان الإقامة:
    Western Atlantic
    Heritage Railway Volunteer:
    No I do not currently volunteer
    Actually, not. As @Steve points out, since the propping is temporary, and will not involve any changes to the permanent structure, there is nothing about it in the application (and thus in the plans therein).

    Still, there's enough detail shown in the images on the page you found to give a good idea what's involved - thanks.

    Noel
     
    Last edited: ‏14 إبريل 2026
    أعجب بهذه المشاركة northernsteam
  14. Enterprise

    Enterprise Part of the furniture

    إنضم إلينا في:
    ‏9 سبتمبر 2005
    المشاركات:
    5,787
    عدد المعجبين:
    3,763
  15. flying scotsman123

    flying scotsman123 Resident of Nat Pres

    إنضم إلينا في:
    ‏9 سبتمبر 2013
    المشاركات:
    10,901
    عدد المعجبين:
    19,603
    الجنس:
    ذكر
    مكان الإقامة:
    Cheltenham
    Heritage Railway Volunteer:
    Yes I am an active volunteer
    To be fair to NYMR, I'm not sure I'd necessarily expect calcs to be released to the public. Even with confidence as low as we all have with the railway atm, I think it's still reasonable to expect someone competent has designed the propping scheme and put their name to it without having to be explicitly told so.

    Sent from my PGT-N19 using Tapatalk
     
    northernsteam, Musket The Dog, jnc و 2 آخرون معجبون بهذا.
  16. Enterprise

    Enterprise Part of the furniture

    إنضم إلينا في:
    ‏9 سبتمبر 2005
    المشاركات:
    5,787
    عدد المعجبين:
    3,763
    I don't mean released to the general public, but an external agency with a purview of the matter. I agree it is reasonable to expect that the analysis has been done, but I have my doubts. Clearly Mr Sash lacks the necessary qualifications.
     
  17. paul1609

    paul1609 New Member

    إنضم إلينا في:
    ‏9 جوان 2006
    المشاركات:
    156
    عدد المعجبين:
    277
    الجنس:
    ذكر
    مكان الإقامة:
    Wittersham, Isle of Oxney
    Heritage Railway Volunteer:
    Yes I am an active volunteer
    Id imagine its a pretty specialist operation especially where the bridge is of mixed construction like this. Id guess that its the same contractor doing the calculations and installing/ hiring the props.
     
  18. iancawthorne

    iancawthorne Well-Known Member

    إنضم إلينا في:
    ‏23 أوت 2010
    المشاركات:
    1,805
    عدد المعجبين:
    6,327
    الجنس:
    ذكر
    مكان الإقامة:
    Brampton, Cumbria
    Scaffolding started to be erected round bridge 42 today.
     
    banburysaint و 47406 معجبون بهذا.
  19. jnc

    jnc Well-Known Member

    إنضم إلينا في:
    ‏3 إبريل 2012
    المشاركات:
    1,702
    عدد المعجبين:
    2,939
    الجنس:
    ذكر
    مكان الإقامة:
    Western Atlantic
    Heritage Railway Volunteer:
    No I do not currently volunteer
    Any chance we could get some images?

    The drawings in We're Proactively Propping Bridge 42 show 4 (two pairs) temporary (presumably) piers, erected in the river bottom, which will have to go in before the propping can be installed.

    Noel
     
  20. 5944

    5944 Resident of Nat Pres

    إنضم إلينا في:
    ‏14 يناير 2006
    المشاركات:
    9,998
    عدد المعجبين:
    11,987
    الجنس:
    ذكر
    الوظيفة:
    Train Maintainer for GTR at Hornsey
    مكان الإقامة:
    Letchworth
    Heritage Railway Volunteer:
    No I do not currently volunteer
    banburysaint, jnc و Kirk Oswald معجبون بهذا.