    Fixed price isn't necessarily as secure as you suggest.
     
    Kempenfelt 82e, pmh_74 и Paul42 нравится это.
  2. Bikermike

    Bikermike Well-Known Member

    Дата регистрации:
    11 мар 2020
    Сообщения:
    1.869
    Симпатии:
    2.099
    Пол:
    Мужской
    Адрес:
    Thameslink territory
    Heritage Railway Volunteer:
    No I do not currently volunteer
    As it happens, I do (it's my day job). I agree no price is ever fixed, but the more risk that is priced and fixed, the more certainty there is.

    Yes, you need to pay more to get more fixity, but you can fix it a lot more than most HS2 contracts were.
     
  3. 35B

    35B Nat Pres stalwart

    Дата регистрации:
    18 июн 2011
    Сообщения:
    29.307
    Симпатии:
    29.816
    Пол:
    Мужской
    Адрес:
    Grantham
    Heritage Railway Volunteer:
    No I do not currently volunteer
    I'd agree on HS2. I'd suggest that the fiasco of the Edinburgh trams shows how tricky it can be to cost those risks properly, and get the right result. I do also recognise that civils may well be more amenable to properly costed risks than my world (commercial IT).
     
  4. Bikermike

    Bikermike Well-Known Member

    Дата регистрации:
    11 мар 2020
    Сообщения:
    1.869
    Симпатии:
    2.099
    Пол:
    Мужской
    Адрес:
    Thameslink territory
    Heritage Railway Volunteer:
    No I do not currently volunteer
    AIUI, Edinburgh trams fiasco was caused by a total failure of the council to understand and manage their contract.

    Civils are less susceptible than (AIUI) IT for eg version/technology change (nobody has updated soil to the best of my knowledge), and you have mucb less risk of "why don't we get it to do x"-itis. However the ground is fundamentally unknown until you dig it.

    The critical point is to de-risk as far as possible, doing surveys/boreholes/trial piys etc. The advantage of telling the contractor they get no more money for ground is to make them much more incentivised to get it right first time. (Equally, you need them to have the time and the resource to do the investigations).

    None of it's rocket science, but the rush to start and the short-term gains of risk-sharing seem to blind everyone to these facts every time.
     
    The Dainton Banker нравится это.
  5. Chris86

    Chris86 Well-Known Member

    Дата регистрации:
    31 окт 2011
    Сообщения:
    1.622
    Симпатии:
    1.858
    Род занятий:
    Safety, technical and vehicle trainer
    Адрес:
    South Yorkshire
    Heritage Railway Volunteer:
    No I do not currently volunteer
    I'm aware of a large civil engineering job that was 2/3 complete, at which point the principle contractor said, due to the rising cost of materials (as a result of Brexit and COVID) they could not complete the job as originally costed- but would finish the work on a cost+ percentage basis to mitigate the risk.
     
  6. 35B

    35B Nat Pres stalwart

    Дата регистрации:
    18 июн 2011
    Сообщения:
    29.307
    Симпатии:
    29.816
    Пол:
    Мужской
    Адрес:
    Grantham
    Heritage Railway Volunteer:
    No I do not currently volunteer
    Precisely my points - and why I'm far from convinced that a fixed price is any more than part of the jigsaw when making sure that a contract will deliver to time and budget. I can well believe that civils are much less susceptible than IT, given my experience in the IT industry is that customers are a) commonly very unwilling to pay for discovery work and b) very poor at understanding the implications of late changes.
     
  7. Bikermike

    Bikermike Well-Known Member

    Дата регистрации:
    11 мар 2020
    Сообщения:
    1.869
    Симпатии:
    2.099
    Пол:
    Мужской
    Адрес:
    Thameslink territory
    Heritage Railway Volunteer:
    No I do not currently volunteer
    a) and (b) are pretty much universal... luckily enough civils clients are repeat buyers who invest in, and trust, their consultants.

    Of course the contract isn't the whole picture, but it's amazing how often laying everyone's duties and liabilities out and having them sign them and not accepting "oh we'll just manage that" or "it'll never happen" flushes a lot out.

    I have only once seen an NEC option C arrangement (a target cost-based contract with pain/gain shares) deliver real value was where the client invested in a pm team that was as big as the contractor's.

    I'm sure the GC team have looked into all this, but in the same way that I don't specify materials, I hope they have had their contracts drawn up by an appropriate professional.
     
    Miff и 35B нравится это.
  8. Bikermike

    Bikermike Well-Known Member

    Дата регистрации:
    11 мар 2020
    Сообщения:
    1.869
    Симпатии:
    2.099
    Пол:
    Мужской
    Адрес:
    Thameslink territory
    Heritage Railway Volunteer:
    No I do not currently volunteer
    And if they'd be going cost+ from the outset, why would that be better?
     
  9. jbg

    jbg New Member

    Дата регистрации:
    19 мар 2018
    Сообщения:
    13
    Симпатии:
    16
    Пол:
    Мужской
    Адрес:
    north yorkshire
    Heritage Railway Volunteer:
    Yes I am an active volunteer
    Most if not all large contracts have clauses related to the price of raw materials, so if they increase (which they always do) so does the contract price, linked to the London Metals Exchange https://www.lme.com/en/ or similar, may well be clauses for energy and building materials, cement, sand gravel etc.
     
  10. gwralatea

    gwralatea Member

    Дата регистрации:
    31 дек 2014
    Сообщения:
    573
    Симпатии:
    1.157
    Пол:
    Мужской
    Heritage Railway Volunteer:
    No I do not currently volunteer
    the obvious example there being the ‘slight’ financial impact on Nuttalls of their complete misreading of what they were likely to find when they built the (original) Lynton and Barnstaple…
     
    Mark Thompson нравится это.
  11. sonicboom

    sonicboom New Member

    Дата регистрации:
    20 дек 2008
    Сообщения:
    33
    Симпатии:
    29
    This is somewhat harsh on the EA. As an Environment Manager with 20+ years of seeking permission for developments / Environment Permits (and also a Friends of the GCR member), EA have done nothing extraordinary here. Though if anyone from the GCR reads this, the EA consultation highlights potential requirement for an Environment Permit for works due to watercourse proximity and if (as the site location plan seems to show) they are that close to the Hermitage brook I'd thoroughly recommend approaching the EA up front over that. Planning permission does not automatically mean granting of an Environment Permit for works.

    https://planningexplorer.charnwood....f&aspectGuid=B8EAB13BDE524DC7985616B5538DDC7F
     
    Chris86, J Rob't Harrison и 35B нравится это.
  12. Mark Thompson

    Mark Thompson Well-Known Member

    Дата регистрации:
    10 сен 2017
    Сообщения:
    1.674
    Симпатии:
    4.141
    Пол:
    Мужской
    Адрес:
    E sussex
    Heritage Railway Volunteer:
    No I do not currently volunteer
    Sure. I did say that it was purely my own opinion, and that it might well prove unpopular;)
     
  13. Sidmouth

    Sidmouth Resident of Nat Pres Staff Member Moderator

    Дата регистрации:
    12 сен 2005
    Сообщения:
    10.189
    Симпатии:
    9.873
    Пол:
    Мужской
    Адрес:
    Alderan !
    Heritage Railway Volunteer:
    Yes I am an active volunteer
    [​IMG]

    rather large fire in the industrial buildings alongside the railway . no indication of any damage to the gcr

    Leicestershire Fire and Rescue Service Loughborough Station


    This morning around 3am (22/06/25) Loughborough fire engine [​IMG] was first in attendance at the Great Central Trading Park which upon arrival was well alight.
    8 Charnwood Police [​IMG] were in attendance to secure the scene and conduct an investigation.
     
  14. Gladiator 5076

    Gladiator 5076 Resident of Nat Pres

    Дата регистрации:
    2 окт 2015
    Сообщения:
    8.228
    Симпатии:
    6.896
    Пол:
    Мужской
    Адрес:
    Swanage
    Heritage Railway Volunteer:
    No I do not currently volunteer
    Fixed price only ever works if you have a VERY well defined specification, plus I would suggest on any construction project no contractor will be prepared to absorb the "unknowns"

    So in many ways fixed price is just a PR myth.
     
  15. Steve

    Steve Resident of Nat Pres Friend

    Дата регистрации:
    7 окт 2006
    Сообщения:
    12.838
    Симпатии:
    12.050
    Род занятий:
    Gentleman of leisure, nowadays
    Адрес:
    Near Leeds
    Heritage Railway Volunteer:
    Yes I am an active volunteer
    Throughout my professional career I’ve always done fixed price contracts. What should also be included in the contracts are extras for any known possible variations and rates for any additional unforeseen work which are paid against signed timesheets. Even in this business when specifying boiler contracts I ask for a price for doing additional stays, changing rivets, etc so that anything that can’t be quantified at the start is covered by the contract at a previously agreed rate. Materials costs are covered by invoice price plus a percentage, again in the contract. Even though the final cost may not be known they are all in effect a fixed price because the rates are agreed in the contract. That’s the only way to avoid being taken for a ride on the inevitable extras.
     
    ghost, gwalkeriow, The Dainton Banker и ещё 1-му нравится это.
  16. Paul42

    Paul42 Part of the furniture

    Дата регистрации:
    17 июл 2006
    Сообщения:
    6.125
    Симпатии:
    4.536
    Пол:
    Мужской
    Адрес:
    East Grinstead
    With regard HS2 one contractors CEO pointed out the design was incomplete, design was also changing, very little ground investigations had been carried out and the full extent of the services to moved was not known.
     
  17. Bikermike

    Bikermike Well-Known Member

    Дата регистрации:
    11 мар 2020
    Сообщения:
    1.869
    Симпатии:
    2.099
    Пол:
    Мужской
    Адрес:
    Thameslink territory
    Heritage Railway Volunteer:
    No I do not currently volunteer
    As Steve says. Fixed price contracts have variation provisions in them. Fluctuations (of which material price changes are a sort) come and go.
    A lot of it is down to commercial positions, but I've yet to see the paying party do better under a cost-plus contract than under a well-scoped and properly understood fixed-price arrangement. (And if you don't know and understand the scope, why are you buying it?)
     
  18. Bikermike

    Bikermike Well-Known Member

    Дата регистрации:
    11 мар 2020
    Сообщения:
    1.869
    Симпатии:
    2.099
    Пол:
    Мужской
    Адрес:
    Thameslink territory
    Heritage Railway Volunteer:
    No I do not currently volunteer
    So the question is then "why the heck did the procuring authority think this a good idea to let the contract"?

    For a variety of good, bad and indifferent reasons construction and civils are very expensive in this country. Anyone not understanding this and planning accordingly should not be let near any project involving a spade in the ground
     
  19. Bikermike

    Bikermike Well-Known Member

    Дата регистрации:
    11 мар 2020
    Сообщения:
    1.869
    Симпатии:
    2.099
    Пол:
    Мужской
    Адрес:
    Thameslink territory
    Heritage Railway Volunteer:
    No I do not currently volunteer
    Yes, but that's not becuase the earth was upgraded to Soil 2.0 during the tender. It was discoverable, and they didn't discover it. Why should that come back to the railway?
     
  20. 35B

    35B Nat Pres stalwart

    Дата регистрации:
    18 июн 2011
    Сообщения:
    29.307
    Симпатии:
    29.816
    Пол:
    Мужской
    Адрес:
    Grantham
    Heritage Railway Volunteer:
    No I do not currently volunteer
    Because ultimately a contract is a commercial deal. In a situation where a contractor can't afford to deliver, the client also has a problem as the previously unknown information is now out in the open.
     
    gwralatea, Gladiator 5076 и Paul42 нравится это.