60007 (4498) Sir Nigel Gresley Overhaul

Discussion in 'Steam Traction' started by No.7, Mar 25, 2016.

  1. marshall5

    marshall5 Well-Known Member

    Joined:
    Oct 26, 2010
    Messages:
    2,376
    Likes Received:
    3,981
    Location:
    i.o.m
    Heritage Railway Volunteer:
    Yes I am an active volunteer
    Let me explain. A tube expander is a series of hardened rollers around the periphery of a steel 'cage'. This is inserted into the tube end (with plenty of oil) right up to the flange on the expander and a tapered mandrel pushed into the expander. There is a square drive on the end of mandrel which can be turned, slowly, by a hand ratchet or a windy drill. As the mandrel turns it screws its way down the expander pushing the rollers out as they turn. This pushes on the inside of the tube wall which expands sealing it in the tube hole. You can see the tube deforming as the expander is turned so tubes are best annealed first. Sometimes the tube may be swaged down and/or jumped up for several inches at the end. IIRC the ones on a Jinty were 1 3/4" dia swaged down to 1 5/8" at the firebox end and jumped up to 1 7/8" at the smokebox end. The idea being that the tube is easier to remove when covered in scale. The expander must be long enough to expand the tube for the full thickness of the tubeplate which is why tubes are trimmed to only leave 3/8 - 1/2" sticking out. The whole process is easier to do than describe, and if doing it by hand, one gets arm muscles like Popeye.
    On firebox tubeplates (and on some smokebox tubeplates) the tubes are beaded over onto the tubeplate using a beading tool - the "hook shape" you described. This can be done by hand or machine.
    The idea of beading is two-fold, to stop the tube end burning away and to protect the tubeplate. Hope this helps.
    Ray.
     
    osprey, ghost, 60017 and 4 others like this.
  2. Steve

    Steve Resident of Nat Pres Friend

    Joined:
    Oct 7, 2006
    Messages:
    11,930
    Likes Received:
    10,088
    Occupation:
    Gentleman of leisure, nowadays
    Location:
    Near Leeds
    Heritage Railway Volunteer:
    Yes I am an active volunteer
    More or less. Rolling is the term used in the US; we tend to say expanding in the UK but it is the same thing. The sealing of the tube to the tubeplate is done in the expanding process. The beading of the tube ends is to prevent them burning away. In the US beading is still quite common on industrial boilers but rarely happens in the UK where we tend to go for welding. You can't do this with a copper firebox on a loco boiler so it has to be by means of beading. Fitting of ferrules to protect the tube end is an alternative to beading but it is a long time since I saw this done with a loco boiler.

    Edit, Marshall5 just beat me to it.
     
    ghost, Bluenosejohn, Kylchap and 2 others like this.
  3. Davo

    Davo Well-Known Member

    Joined:
    Oct 12, 2018
    Messages:
    1,523
    Likes Received:
    634
    Gender:
    Male
    Location:
    W yorkshire 56f
    Heritage Railway Volunteer:
    No I do not currently volunteer
    Thanks to you both marshall5 and steve for that explanation on this subject. I've been looking all over Google sites to see if I could find anything about tube fitting. I came across a few You Tube vids on demos. Mainly Yankee boiler smithies fitting tubes and showing how rolling and beading is done.
     
    Last edited by a moderator: Feb 5, 2019
  4. Kylchap

    Kylchap Member

    Joined:
    Dec 15, 2015
    Messages:
    463
    Likes Received:
    840
    Gender:
    Male
    Location:
    East Anglia
    Heritage Railway Volunteer:
    No I do not currently volunteer
    Thanks for the very interesting technical explanations above.
     
  5. Steve

    Steve Resident of Nat Pres Friend

    Joined:
    Oct 7, 2006
    Messages:
    11,930
    Likes Received:
    10,088
    Occupation:
    Gentleman of leisure, nowadays
    Location:
    Near Leeds
    Heritage Railway Volunteer:
    Yes I am an active volunteer
    More on tubing. You've mentioned tubes being swaged up and tubes being swaged down. Main line loco practice is generally for the tubes to be swaged down at the firebox whilst industrial loco practice is generally for tubes to be swaged up at the smokebox end, although, as you say, both can be applied. The advantage of the former is that the ligaments between the tubes are larger, making them less liable to fracture whilst the advantage of the latter is that the tubes are generally easier to remove when covered in scale. The diagram below shows the difference between two otherwise identical tube arrangements.
    upload_2019-2-4_22-20-10.png
     
    ghost, CH 19, 60017 and 3 others like this.
  6. CH 19

    CH 19 Well-Known Member Friend

    Joined:
    Dec 30, 2013
    Messages:
    1,255
    Likes Received:
    632
    Gender:
    Male
    Location:
    W14
    Heritage Railway Volunteer:
    No I do not currently volunteer
    Like Kylchap, thank you all for the explanations, tis so good for me to be able to increasingly understand the technical side of our passion.

    Chris
     
  7. estwdjhn

    estwdjhn Member

    Joined:
    Jan 24, 2013
    Messages:
    325
    Likes Received:
    641
    Occupation:
    Boilermaker
    Heritage Railway Volunteer:
    Yes I am an active volunteer
    The advantage to "mainline practice" is increased heating surface, as for a given size of tube holes one gets to use tubes which are a size larger.

    There are also locos about which have the tubes swaged down at the firebox end, and swaged up in the front tubeplate (the front tubeplate is often very thick, which then permits a certain amount of reduction in the ligaments size) - to some extent this arrangement is a "best of both worlds".
     
  8. 60017

    60017 Resident of Nat Pres Friend

    Joined:
    Jul 6, 2008
    Messages:
    9,002
    Likes Received:
    7,891
    Gender:
    Male
    Occupation:
    Retired from corporate slavery :o)
    Location:
    Fylde Coast
    Heritage Railway Volunteer:
    No I do not currently volunteer
    From the SNGLT website (members area) today...


    Update 24 April:

    The overhaul of our locomotive achieved a significant milestone yesterday when the boiler successfully passed its formal hydraulic test to the satisfaction of our insurers. A steam test will follow shortly. The superheater needs to be re-fitted after which the boiler will be moved to York and reunited with the frames. It is envisaged a further in-frames hydraulic test will be conducted during the re-assembly process to reset the clock on the ten year boiler approval.
     
  9. garth manor

    garth manor Well-Known Member

    Joined:
    Apr 10, 2009
    Messages:
    1,690
    Likes Received:
    450
    Thanks for spotting that, good progress for a much needed A4 working presence.
     
    Wingsandwheels likes this.
  10. Davo

    Davo Well-Known Member

    Joined:
    Oct 12, 2018
    Messages:
    1,523
    Likes Received:
    634
    Gender:
    Male
    Location:
    W yorkshire 56f
    Heritage Railway Volunteer:
    No I do not currently volunteer
    Any news on when a move of 60007,s boiler is moved back to N.R.M.? Then early to mid summer im presuming if a out of frames steam test is to take place.
    Good news on the hydraulic test.:)
     
  11. 60017

    60017 Resident of Nat Pres Friend

    Joined:
    Jul 6, 2008
    Messages:
    9,002
    Likes Received:
    7,891
    Gender:
    Male
    Occupation:
    Retired from corporate slavery :o)
    Location:
    Fylde Coast
    Heritage Railway Volunteer:
    No I do not currently volunteer
    Not yet. Be patient!
     
  12. Davo

    Davo Well-Known Member

    Joined:
    Oct 12, 2018
    Messages:
    1,523
    Likes Received:
    634
    Gender:
    Male
    Location:
    W yorkshire 56f
    Heritage Railway Volunteer:
    No I do not currently volunteer
    Ok john.:Morewaitingisrequired:
     
  13. Eightpot

    Eightpot Resident of Nat Pres Friend

    Joined:
    Aug 10, 2006
    Messages:
    8,077
    Likes Received:
    2,264
    Gender:
    Male
    Occupation:
    Engineer Emeritus
    Location:
    Aylesbury
    Heritage Railway Volunteer:
    Yes I am an active volunteer
    Snap! Got my 5" gauge LNER V1 2-6-2 tank loco boiler hydraulically tested successfully today by the local model engineering club.
     
    Davo, 242A1, Johnb and 1 other person like this.
  14. Davo

    Davo Well-Known Member

    Joined:
    Oct 12, 2018
    Messages:
    1,523
    Likes Received:
    634
    Gender:
    Male
    Location:
    W yorkshire 56f
    Heritage Railway Volunteer:
    No I do not currently volunteer
    update from rail advent 28th/5/2019 written by jamie duggan issue 40 engineering update on A4 60007 S.N.G. latest restoration work of tender and middle valve gear components and more......
    Check the link above Davo 56F.
     
  15. Thompson1706

    Thompson1706 Part of the furniture

    Joined:
    Nov 19, 2007
    Messages:
    2,438
    Likes Received:
    1,844
    Gender:
    Male
    Occupation:
    Retired
    Location:
    Rhiwabon
    Heritage Railway Volunteer:
    Yes I am an active volunteer
    A fire was lit this morning to warm up the boiler in readiness for its steam test.

    Bob.
     
  16. pwsw5054

    pwsw5054 Member

    Joined:
    Jan 5, 2016
    Messages:
    396
    Likes Received:
    1,180
    Gender:
    Male
    Heritage Railway Volunteer:
    Yes I am an active volunteer
    Boiler steam testing has started at Llangollen, this is part of a series of tests leading to the formal insurance test when the superheater header has been fitted. The fire was first lit on 23rd May 2019, 60 years after 60007 set the post war speed record.

     
  17. Eightpot

    Eightpot Resident of Nat Pres Friend

    Joined:
    Aug 10, 2006
    Messages:
    8,077
    Likes Received:
    2,264
    Gender:
    Male
    Occupation:
    Engineer Emeritus
    Location:
    Aylesbury
    Heritage Railway Volunteer:
    Yes I am an active volunteer
    Just one quibble with this. From my experience isn't it more of a case of the tube being initially rolled and expanded so that it is in contact all round with the hole in the tube plate, then being squeezed between the rollers of the expander and the tube plate, which results in the circumference of the tube being stretched and thus made larger in diameter to effect a seal? A bit difficult to find words to describe the procedure, but hope you understand what I mean.
     
    Last edited: Jun 1, 2019
    Gwrman 1985 likes this.
  18. Davo

    Davo Well-Known Member

    Joined:
    Oct 12, 2018
    Messages:
    1,523
    Likes Received:
    634
    Gender:
    Male
    Location:
    W yorkshire 56f
    Heritage Railway Volunteer:
    No I do not currently volunteer
    Reaming the tube ends?
     
  19. 61624

    61624 Part of the furniture

    Joined:
    Sep 27, 2006
    Messages:
    5,294
    Likes Received:
    3,596
    Heritage Railway Volunteer:
    Yes I am an active volunteer
    Expanding a tube to fit a hole in a tube plate is not reaming as I understand it, which is finishing a hole to a precise size
     
  20. Sheff

    Sheff Resident of Nat Pres

    Joined:
    Apr 21, 2006
    Messages:
    7,568
    Likes Received:
    2,345
    Gender:
    Male
    Occupation:
    Retired Engineer & Heritage Volunteer
    Location:
    N Warks
    Heritage Railway Volunteer:
    Yes I am an active volunteer
    Do you mean beading-over?


    Sent from my iPhone using Tapatalk
     