    The "Gap" website has now been updated to say that it is only a few days until the main bridge sections are lifted into place, and "more details are to follow.."
     
    jnc likes this.
  2. ilvaporista

    ilvaporista Part of the furniture

    Joined:
    Jan 16, 2006
    Messages:
    4,250
    Likes Received:
    5,321
    Gender:
    Male
    Occupation:
    C.Eng
    Location:
    On the 45th!
    Have the bridge beams arrived at the site ready for the lift?
     
  3. Johann Marsbar

    Johann Marsbar Well-Known Member

    Joined:
    Feb 21, 2016
    Messages:
    1,592
    Likes Received:
    2,010
    Gender:
    Male
    Location:
    Suffolk
    Heritage Railway Volunteer:
    No I do not currently volunteer
    One hopes so, as they have now posted full details on the Gap website of what is taking place, together with viewing information.
    Network Rail MML possession is 00.30-07.00 Sunday for any insomniacs interested.....
     
    ilvaporista likes this.
  4. AndyY

    AndyY Member

    Joined:
    Feb 23, 2013
    Messages:
    433
    Likes Received:
    480
    On Facebook it says "I have been informed by Moores that the Bridge sections will be loaded Saturday morning are being transported by road via the A47 then round by the bypass to Loughbrough Sat morning and should be on site by midday.They also said that the Deck was not due to be with the Girders".

    My interpretation of the info so far is that the two side girders of the bridge will be lifted in this weekend, and then steel deck installed over the next couple of weeks. Will this still need the big crane?

    Andy
     
    Black Jim and jnc like this.
  5. David R

    David R Well-Known Member

    Joined:
    Jul 30, 2013
    Messages:
    1,018
    Likes Received:
    1,386
    Gender:
    Male
    Location:
    Surrey
    Heritage Railway Volunteer:
    Yes I am an active volunteer
    Silly Question time - are they side girders? The website refers to them being box girder sections - don't these normally sit under the deck?

    David R
     
  6. AndyY

    AndyY Member

    Joined:
    Feb 23, 2013
    Messages:
    433
    Likes Received:
    480
    I may well be using the wrong term and making a bridge-designer wince - bridge beams, side girders, box girders?
    I seem to recollect a cross-section in the GCR magazine showing a trapezoidal-section box either side with the deck linking the bottom so the boxes effectively form 'walls' either side of the track. But of course the final design might be different!
     
    David R likes this.
  7. mogulb

    mogulb New Member

    Joined:
    Dec 20, 2010
    Messages:
    125
    Likes Received:
    95
    AndyY. You are spot on that is what is being installed. (Not sure of the correct technical terminology though.)

    Logically the large crane will disappear fairly swiftly and considerably smaller cranes used to install the remaining components over the coming weeks.
     
  8. AndyY

    AndyY Member

    Joined:
    Feb 23, 2013
    Messages:
    433
    Likes Received:
    480
    I've been wondering whether the big crane will still be needed to reach far enough, but if the deck will take a fortnight to install it would be expensive to keep the big one. I'm assuming installing the deck will also have to be done during overnight possessions of the Midland line below.
     
  9. mogulb

    mogulb New Member

    Joined:
    Dec 20, 2010
    Messages:
    125
    Likes Received:
    95
    All the remaining components will be small and fairly light compared to the main beams, so can be craned in from both sides, a one ton lift at say 25m radius would not require a huge crane. If the big crane stays I would assume they would attempt to install everything else in one possession, unlikely to happen unless the contractors have a very extra special deal with Baldwins or the crane is not needed elsewhere. Mostly conjecture but We should know by Monday/ Tuesday . Hope this helps a bit.
     
  10. AndyY

    AndyY Member

    Joined:
    Feb 23, 2013
    Messages:
    433
    Likes Received:
    480
    The GCR website says "The new bridge is a "box girder" construction, with the two main sections being installed this weekend and followed in the coming weeks by the installation of 20 tonne steel plates which will form the main deck."
    So some 20 tonne plates to lift into place. It doesn't say how many.
    It's fascinating to see it all coming together.
    Andy
     
  11. mogulb

    mogulb New Member

    Joined:
    Dec 20, 2010
    Messages:
    125
    Likes Received:
    95
    AndyY. I think the 20 t is all the remaining steelwork as the bridge weighs in total 100t. There are approx 60 cross beams to install and then steel plate on top of them to take the ballast and track. There are a couple of drawings viewable on the Charnwood Borough council planning portal. Bit fiddly to find , but can be found if you search under Great Central Railway.
     
    Black Jim and jnc like this.
  12. mogulb

    mogulb New Member

    Joined:
    Dec 20, 2010
    Messages:
    125
    Likes Received:
    95
    robpalmer, Bean-counter, jnc and 4 others like this.
  13. Ploughman

    Ploughman Part of the furniture

    Joined:
    Apr 1, 2008
    Messages:
    5,815
    Likes Received:
    2,656
    Occupation:
    Ex a lot of things.
    Location:
    Near where the 3 Ridings meet
    Heritage Railway Volunteer:
    Yes I am an active volunteer
    I take it all went to plan and no delays.

    Congratulations to all involved.
     
  14. AndyY

    AndyY Member

    Joined:
    Feb 23, 2013
    Messages:
    433
    Likes Received:
    480
    Splendid news! The 'end of the beginning'.

    There's no longer any excuse for the sceptics to doubt that this project will be completed, the timescale will just be determined by the rate that funding can be raised.
     
  15. Kinghambranch

    Kinghambranch Well-Known Member

    Joined:
    Dec 20, 2006
    Messages:
    1,872
    Likes Received:
    1,590
    Gender:
    Male
    Occupation:
    Retired
    Location:
    White Rose County
    Heritage Railway Volunteer:
    No I do not currently volunteer
    I'm not too proud to admit that I was always very sceptical about this project ever happening in reality. Just goes to show, what do I know eh? Definitely the end of the beginning now and congratulations to all involved and for having more faith than I had.:Joyful:
     
  16. J Rob't Harrison

    J Rob't Harrison Member

    Joined:
    Nov 6, 2016
    Messages:
    222
    Likes Received:
    316
    Gender:
    Male
    Location:
    Stafford
    Heritage Railway Volunteer:
    No I do not currently volunteer
    Having supported the project since it was first formally announced four (five?) years ago, it is very satisfying to see the first part of it nearing completion.

    "With the bridge complete, attention will move to the next phase of the gap project...."

    So, what's the next phase? Let's keep the momentum up!
     
  17. crantock

    crantock Member

    Joined:
    Nov 22, 2008
    Messages:
    527
    Likes Received:
    276
    Gender:
    Male
    Occupation:
    Beancounter
    Location:
    Birmingham
    Heritage Railway Volunteer:
    No I do not currently volunteer
    Congratulations. But It's 10.40 and it's 2017. I can not find a daylight photo on the net.

    Anyone want to be a keyboard hero?


    Sent from my iPhone using Tapatalk
     
  18. J Rob't Harrison

    J Rob't Harrison Member

    Joined:
    Nov 6, 2016
    Messages:
    222
    Likes Received:
    316
    Gender:
    Male
    Location:
    Stafford
    Heritage Railway Volunteer:
    No I do not currently volunteer
  19. Black Jim

    Black Jim Member

    Joined:
    Oct 21, 2009
    Messages:
    468
    Likes Received:
    166
    At last! Bleddy marvellous thing to happen! I was on the railway in the early 90s , but since moving away have kept an eye on things , a lot through this website.
     
  20. Reading General

    Reading General Part of the furniture

    Joined:
    May 18, 2011
    Messages:
    6,081
    Likes Received:
    2,217
    I had no idea this project was so advanced. Well done everyone concerned
     

Share This Page