2017 January - Long Weekend Working Party Progress Report

Discussion in 'On Track.' started by Karen Willans, Jan 30, 2017.

    20-23 January 2017


    Friday

    The morning was spent completing the fitting of the motion to William Finlay and placing in its final position. We also tidied up around ‘William’ and removed the surplus packing material from the museum and stacked it appropriately. We carried out a line inspection between Wharf and Pendre as well as removing a large quantity of grass and weeds growing in the ballast. An audit of the sleepers at Wharf was also carried out.

    Saturday

    Saturday was ‘Line inspection day’. We made a start at Abergynolwyn, first we went to Nant Gwernol, then to Quarry Siding. The hedging gang who were carrying out some prep work with a train kindly gave us a ride back to Abergynolwyn for lunch. After lunch we drove to Brynglas and inspected the line between there and Quarry Siding. While the line inspections were being carried out others used the pole saw to remove overhanging branches on the same sections.



    Sunday
    On Sunday we split the available gang between leaf removal with the leaf blowers and future work planning linked to further line inspection work. We also took a quantity of scrap to Wharf and obtained additional fuel for the leaf blowing gang. The leaf blowing gang started at Quarry Siding and headed west. We remove the leaves for several reasons including fouling the drainage and making line inspections very difficult. The leaves in places along the line collect in huge drifts nearly a foot deep. Line inspections were carried out between Pendre and Hendy Bridge and Rhydyronen and Brynglas.

    Monday

    The day was spent continuing with the leaf removal west of Dolgoch and clearing the drains. They made excellent progress and by the close of play they were about 100metres west of 4 ½ milepost.



    Very many thanks to everyone who came along to enjoy three days of sunshine and help with tasks outlined above. The weather was a little chilly at times but it did not stop the good work. Many thanks again, your assistance is much appreciated.

    Forthcoming opportunities to help your railway:

    • Long Weekend 10-13 February 2017
    • Spring Outdoor Week 25 Feb -5 March 2017

    Advance notice is always very helpful!

    Report by Keith Theobald
     